Guide · 5 min read

What a High-End Renovation Timeline Looks Like

The three phases of a serious renovation, what happens in each, and the decisions that keep a programme on track.

“How long will it take?” has an honest answer: it depends on decisions made before anyone lifts a tool. A well-run renovation has three phases, and the calendar is largely written in the first one.

Phase 1 — Pre-construction (8–12 weeks)

Design development, structural engineering, planning or permitted-development confirmation, party-wall notices, and specification. It feels slow because nothing is visibly happening — but every week invested here removes two weeks of on-site improvisation later. This is also when long-lead items must be ordered: windows, steels, kitchens and stone all carry lead times that can exceed the build phase itself.

Phase 2 — Primary works (16–24 weeks for a full renovation)

Strip-out, structural alterations, and first-fix services — the unglamorous middle where the property looks worse before it looks better. Progress here is measured in inspections passed: structure signed off, first-fix electrics and plumbing approved, insulation checked. A property that reaches plastering with every inspection passed is a project that finishes on time.

Phase 3 — Finishing (8–12 weeks)

Plastering, second-fix services, joinery, tiling, decoration and commissioning. Counter-intuitively this is the phase most often rushed — and the one your eye lives with every day afterwards. We protect the finishing programme deliberately: it is where a project earns its photographs.

What moves a timeline

  • Decision speed. Every unmade choice — tiles, brassware, paint colours — eventually blocks a trade. We give you a decision schedule so choices are made before they are needed, not after.
  • Lead times. Bespoke glazing, stone and joinery can run 6–12 weeks. Ordered in pre-construction, they arrive on cue; ordered late, they stall the site.
  • Discoveries. Opened-up structures sometimes disagree with the drawings. A contingency plan (and budget) keeps discoveries from becoming delays.
  • Weather. Roofs, externals and open structures are hostage to it; we sequence weather-dependent work with float either side.

Smaller projects, shorter clocks

ProjectTypical time on site
Bathroom renovation2–3 weeks
Kitchen renovation3–5 weeks
Dormer loft conversion8–12 weeks
Single-storey extension10–16 weeks
Full-house renovationSee three phases above

We confirm a programme in writing before work begins and report progress against it weekly — if a date moves, you hear it from us first, with the reason and the recovery plan.